Guides

Strata Repairs and Defects in Australia: Who Fixes What and Who Pays (2026)

Leaks, waterproofing, mould, roofs, drains, glass, gates, fire safety and new-building defects: who has to fix each one, who pays, what to do first and how to make a slow owners corporation act. State-by-state, written for owners and committees.

By Buddy · · 18 min read

On this pageHow to use this guide
  1. How to use this guide
  2. Table of contents
  3. The rule that settles most repair arguments
  4. Water leaks from above
  5. Bathrooms, showers and balcony waterproofing
  6. Mould and condensation
  7. Roofs, gutters and stormwater
  8. Pipes, drains, flexi hoses and wet wipes
  9. The small parts that fail: glass, gates and chutes
  10. Fire safety and cladding
  11. Defects in a new building
  12. When the owners corporation will not act
  13. Planned maintenance, painting and running costs
  14. State-by-state quick reference
  15. New South Wales
  16. Victoria
  17. Queensland
  18. Western Australia
  19. South Australia
  20. Tasmania
  21. Australian Capital Territory
  22. Northern Territory
  23. The legal layer under the repair bill
  24. Tools for owners and committees
  25. Frequently asked questions
  26. Water is coming through my ceiling. Who pays?
  27. Is my shower membrane mine or the building's?
  28. The strata says they can't afford the repair. Can they wait?
  29. How long do I have to claim against the builder?
  30. Will strata insurance pay for it?
  31. Who fixes a blocked drain?
  32. Can the building charge me for damage I caused?
  33. Keep reading

Most repair fights in an apartment building are not really about the repair. They are about who pays for it. The water came through your ceiling, but did it start in a pipe that serves one lot or six? The shower leaks, but is it the grout or the membrane under it? The building is three years old, so is this the owners corporation's problem or the builder's?

Those questions have answers. The answers depend on the registered plan, the state Act, the by-laws, and how old the building is. This guide puts them in one place for the people who live with the result: lot owners, tenants who need a fix, and the committee members who have to decide what to spend.

It pulls together everything UnitBuddy has published on repairs, maintenance and building defects. Each section gives you the working answer and then points to the full article when you need the detail.

How to use this guide

If something is leaking or broken right now, read the rule that settles most repair arguments first, then jump to the section for your problem. Each section stands on its own.

If you are on a committee, read it in order before your next capital works review or AGM. The order runs from everyday failures to the expensive ones: water, wet areas, mould, roofs and drains, the small parts that break, fire safety, new-building defects, and the slow work of planned maintenance.

If your building keeps fixing the same thing every year because nobody can find last year's report, that is the problem UnitBuddy was built to solve.


Table of contents

  1. The rule that settles most repair arguments
  2. Water leaks from above
  3. Bathrooms, showers and balcony waterproofing
  4. Mould and condensation
  5. Roofs, gutters and stormwater
  6. Pipes, drains, flexi hoses and wet wipes
  7. The small parts that fail: glass, gates and chutes
  8. Fire safety and cladding
  9. Defects in a new building
  10. When the owners corporation will not act
  11. Planned maintenance, painting and running costs
  12. State-by-state quick reference
  13. The legal layer under the repair bill
  14. Tools for owners and committees
  15. Frequently asked questions

The rule that settles most repair arguments

Responsibility follows the thing that failed, not the room where the damage shows up.

If the failed part is common property, the owners corporation (body corporate in Queensland, strata company in Western Australia) must repair it and pays from levies. If the failed part belongs to a lot, that lot's owner fixes it. Where the water lands, where the mould grows and whose ceiling is stained do not decide anything.

What counts as common property comes from the registered plan and the state Act. In New South Wales, for plans registered after 1 July 1974, the lot boundary is usually the inner face of the walls, floors and ceilings. External walls, roofs, slabs, façades, windows and balcony doors, waterproofing membranes, common stacks and any pipe serving more than one lot sit outside it. Tiles, internal fittings, surface finishes and branch pipes serving one lot are usually lot property. Queensland and parts of Victoria draw the line differently, so check your plan before you argue.

Every Australian jurisdiction puts a duty on the owners corporation to keep common property in repair. In NSW it is of the , and it is strict: lack of money, lack of knowledge or a committee vote is not a defence. In Victoria it is of the . Queensland's and Western Australia's reach the same result.

Two practical rules follow from this:

  • Find the source before anyone pays for a clean-up. A licensed plumber, leak detector or building consultant should say in writing which component failed and whether it is common property or lot property.
  • Put everything in writing. Photos, dates, the report, the request. A phone call to the strata manager is not a record.

Water leaks from above

Whoever owns the place the water starts pays to stop it. A failed membrane or a pipe serving more than one lot is the owners corporation's. A burst flexi hose, a leaking tap, an overflowing washing machine or a pipe serving only the upstairs lot is the upstairs owner's.

Do the first five days in this order:

  • Day 1. Written notice with photos to the owners corporation and the upstairs occupier. Isolate the water if it is safe.
  • Days 2 to 3. A licensed plumber or leak detector says, in one paragraph, whether the source is common property or a lot.
  • Day 4. If the source looks like common property, the committee authorises opening up.
  • Day 5. Both owners get the report, and both tell their insurers.

The scheme's building policy under may respond to sudden damage. It often will not respond to slow failure, and a $7,500 excess on a $4,000 ceiling means nobody claims. An insurer's decline does not cancel the owners corporation's repair duty.

When the leak comes from common property and the owners corporation drags its feet, a NSW owner can recover repairs to lot property, rental loss, alternative accommodation and expert fees. You still have to mitigate your loss. If the source is the upstairs lot, the claim is against that owner, and bars an owner from using a lot in a way that causes a nuisance or hazard.


Bathrooms, showers and balcony waterproofing

Waterproofing is the most common serious defect in new NSW apartments. Building Commission NSW research puts it at about 42 per cent of serious defects in Class 2 buildings.

Split the bathroom into layers before you decide who pays:

  • Silicone, grout and tile adhesive are the lot owner's, everywhere.
  • The membrane under the tiles follows the state and the plan. In NSW it is almost always common property, so the owners corporation repairs it. In Queensland, a bathroom membrane in a building format plan is usually the lot owner's (). In Victoria it depends on the plan: put tiles and membrane on the lot side of an interior-face plan, and held a balcony membrane on an older plan was common property. In WA it is often common property.
  • Common pipework is the owners corporation's.

Balconies are usually part of the building envelope. In Queensland, made the body corporate responsible for a terrace membrane in an exclusive-use area, including access and reinstatement costs.

If you are renovating in NSW, bathroom work that affects waterproofing is not a minor renovation under . It needs a special resolution at a general meeting. Pair it with a by-law that hands maintenance of the new membrane to the renovating owner, or the next failure lands back on everyone.

White powder on brick, render or a car park soffit is efflorescence, and it is a water symptom. Brush it off dry. Do not hose it, paint it or seal it until the water source is fixed, because sealer traps the salts behind the surface and can spall the brick. On a building less than a year old it is usually new-building bloom. Crusts, drips and stalactites from a car park slab mean it is time for an engineer.


Mould and condensation

Mould follows moisture, and responsibility follows the moisture source. The common sources, in order of how often they turn up, are leaks from common property, condensation from poor ventilation, cold external walls, and leaks from a neighbouring lot. The first three are usually common property problems. The fourth may be the neighbour's.

Some mould really is how the apartment is lived in. A household releases around eight litres of water into the air every day, and a load of washing dried indoors adds several more. Indoor humidity that stays above 60 per cent means the problem is still live. A $20 hygrometer will tell you.

My view: get the diagnosis before you pay for the clean. A specialist moisture and mould inspection costs roughly $400 to $800 and names the source. A multi-room remediation can run well past $3,000, and if the source is still there the mould comes back. The inspection fee is recoverable from the owners corporation if common property turns out to be the cause.

The order is the same everywhere: diagnose, fix the source, remediate, then check the humidity again. Strata building insurance covers sudden and accidental damage. Gradual condensation, long-term leaks and wear-and-tear mould are routinely excluded.


Roofs, gutters and stormwater

The roof, box gutters, outlets, downpipes, ground-level pits, driveways, trench drains, sump pits, pumps and the private stormwater line to the street are common property in almost every state. The owners corporation maintains them and cannot push that onto lot owners. Balcony drains depend on the state and the plan. Some townhouse and villa schemes have by-laws that hand roof maintenance to individual owners, so read yours.

Most roof leaks come from five places: box gutters, flashings at parapets and walls, penetrations added later (solar mounts, air-conditioning pipes, antennas, especially where they were sealed with silicone alone), lifted or corroded sheets, and cracked ridge bedding. Sydney's storm season runs from about October to March. Clean the gutters, valleys and outlets at least twice a year and before each storm season.

Drainage is where small savings turn into big claims. A blocked driveway trench that costs a few hundred dollars a year to clean can become a $30,000 to $200,000 basement flood. A failed sump pump with no service log turns the insurance claim into a fight. For a 60-lot building the full pre-winter program can run under $10,000 a year.


Pipes, drains, flexi hoses and wet wipes

The plumbing rule is simple, and the plan decides the edge cases. A pipe serving more than one lot is generally the building's to repair. A pipe serving one lot, sitting inside that lot and not inside a common property wall, floor or ceiling, is generally the owner's. A sewer line under one owner's courtyard is still common property if three units drain through it. In Queensland, stops an exclusive use by-law from handing utility infrastructure that is common property to one owner.

Recurring blockages. Many walk-ups built from the 1950s to the 1980s still run on terracotta sewer pipes, and tree roots grow in through the joints. Jetting cuts the roots but does not close the joint. Log every blockage, get a CCTV inspection on the next clear, and compare the cost of clearing it again with a relining quote. Repeated clearing is an admin fund cost. Relining belongs in the capital works plan.

Flexi hoses. The hose after your isolation valve is yours. Between 20 and 24 per cent of Australian household water damage claims come from flexi hoses splitting, and a typical apartment claim is now over $27,500. Hoses are built to last 5 to 10 years. A coordinated building-wide replacement costs $200 to $400 a lot. Every claim, even one the insurer pays, pushes up the building's premium.

Wet wipes. The toilet and any in-apartment macerator belong to the lot. The stack, junctions, ejector pit and pumps are common property, so the owners corporation pays the emergency plumber first. Recovering that cost from one lot needs a by-law, evidence that identifies the source, and a written notice. An ejector pump replacement costs $8,000 to $20,000. No wipe should be flushed, whatever the packet says.

For residents who want the plumbing basics without the legal detail, the free building guides explain water, drains, lifts and bins in plain English, with no account needed.


The small parts that fail: glass, gates and chutes

These are cheap parts on expensive cycles. They break often, and each break is an invoice.

Balcony glass doors. In most NSW schemes registered after 1 July 1974 the balcony door is common property, so the owners corporation replaces it and claims on the building policy, or on the builder if the building is young. A committee cannot shift that onto you by ordinary resolution or email. Only a by-law can. The usual cause of a spontaneous break is a tiny nickel sulphide stone in the glass. If yours goes, keep people away, photograph everything before you sweep, keep the fragments from where the break started, and do not book your own glazier for a common property door unless the owners corporation agrees.

Garage doors and boom gates. The basement roller door, boom, sliding gate and readers are common property in almost every plan, so the owners corporation pays the first invoice, even after a resident drives into it. Recovery from the driver comes later and needs evidence: a plate-capture still, the operator's event log and a technician report that the safety sensors were working. A 50-lot building can cycle its door 60 to 120 times a day, so springs and operators wear out on a schedule. Plan the replacement, or pay after-hours rates for it.

Garbage chutes. The chute, hoppers, liners, fire dampers and compactors are common property. A jammed hopper or a torn liner is a building invoice unless a resident put something down the chute the by-laws say must not go there. Do not invent a chute fine. A notice to comply plus recovery of the contractor's invoice is the path that survives a tribunal. A compactor fire that sets off the chute sprinklers can cost $50,000 to $200,000.


Fire safety and cladding

Fire safety is not optional maintenance, and it does not wait for the next AGM.

In NSW, from 13 February 2026, essential fire safety systems must be inspected and tested under AS 1851 unless the building has an applicable performance solution. That means a physical logbook on site, baseline data for every system and records kept for seven years. It does not mean you must upgrade the systems you have. You must prove in writing that you maintain them. The owners corporation gives the Annual Fire Safety Statement to council and Fire and Rescue NSW and displays it in the building.

Most fire defects are admin fund maintenance. Replacing a fire panel, a hydrant booster or a full detection system is capital and should already be in the 10-year plan. When two inspection reports disagree, do not pick the cheaper one and do not average them. Line them up measure by measure against the fire safety schedule. If the argument is about which historic standard applies, pay a fire engineer for a short opinion.

Other states use different certificates for the same job: the Essential Safety Measures Statement in Victoria and the BFSR in Queensland.

Combustible cladding is the expensive end. Full rectification typically runs $15,000 to $50,000 a lot, and more on complex buildings. Insurance premiums on affected buildings can be two to five times higher. Victoria has the most advanced government program, through Cladding Safety Victoria. NSW offers interest-free loans through Project Remediate. In Queensland, WA and most other states, owners largely carry the cost.


Defects in a new building

In a newer building the repair duty and the defect claim run side by side. The owners corporation still has to make common property safe and working now. The builder, developer, certifier and product suppliers may have to pay for it later. Keep the two tracks apart, so the claim does not hold up urgent repairs.

In NSW the gives statutory warranties under . Under the period is six years from completion for a major defect and two years for other defects. Waterproofing can be a major defect, but the label is not automatic. The adds a duty of care owed by builders, designers and manufacturers, and it extends to later owners.

The clock usually starts at completion, not when you find the defect, and defects are slow to show. In the Building Commission NSW 2025 survey, 21 per cent of buildings registered in 2024 reported serious defects, against 69 per cent of buildings registered in 2018. Occupants were the first to spot them in 63 per cent of buildings. Building bond inspections found them in 12 per cent. A clean first year proves very little.

The money is worse than most owners expect. Across 211 NSW buildings with serious defects, only 54 per cent of the roughly $45 million spent went on rectification. Professional fees took 25 per cent and legal costs 19 per cent. Only 17 of the 211 buildings recovered any money. Opal Tower shows what it looks like when it goes well: the builder fixed the building, but only after owners went to court, and the owners corporation paid for engineers, project managers and lawyers long before any money came back.

A builder's "yes" is the start of the job, not the end of it. Turn an agreed repair into a schedule, item by item: what is being fixed, who approves changes, who checks the finished work, and what counts as complete. In the same NSW research, 53 per cent of the buildings that resolved every serious defect did it by negotiation, against 13 per cent through litigation.


When the owners corporation will not act

The excuses are familiar, and in NSW none of them works. "We don't have the funds" fails, because the owners corporation can raise a special levy or borrow. "We're waiting for the developer" fails, because the owners corporation can fix first and recover later. "It's your lot" fails when the failed part is the membrane, roof, external wall, window or structure. "The committee voted against it" is a breach of the duty with a vote attached.

The escalation path in NSW:

  1. Written notice to the committee chair and the strata manager, citing , with photos and a deadline of 14 to 28 days.
  2. A general meeting motion. Owners holding at least 25 per cent of unit entitlements can requisition one.
  3. A complaint to NSW Fair Trading, which since 27 October 2025 can issue compliance notices under and accept enforceable undertakings under . It is free for the owner.
  4. Mediation, which is required before NCAT hears most strata disputes and usually takes 4 to 8 weeks to arrange.
  5. NCAT, which can order the work done and award damages. Hearings are typically within 3 to 6 months.

Since 1 July 2025 a NSW owner has six years, up from two, to claim damages for breach of the repair duty, counted from when they first became aware of the loss ().

The sequence is broadly the same in other states: written notice, evidence, a decision by the corporation, the local mediation or dispute process, then the tribunal or court.


Planned maintenance, painting and running costs

Reactive repair costs five to ten times what a planned program would. Most of this guide is about things that broke. This section is about the work that stops them breaking.

Running costs. A 60-lot building often spends $50,000 to $150,000 a year on maintenance before insurance, management and utilities. Lifts are usually the biggest line, and untendered lift contracts often pay 20 to 40 per cent more than market. Build an asset register with install dates, service history and replacement year, and tender the big contracts every three to five years on a written scope.

Repainting. There is no statutory repaint interval anywhere in Australia. The duty is condition-based. Start with a condition inspection, not a painting quote, because the scaffold finds spalling, failed sealant and membrane work the paint quote did not price. Repainting in the same colours is maintenance. A new look is an improvement that needs a special resolution, under in NSW or in Victoria. In Queensland standard format (townhouse) schemes, exterior painting is each owner's job, and the body corporate cannot save up to do it for them.

Accessibility. A grab rail inside the lot is the owner's project. A ramp, an automatic lobby door or a handrail on common property is the owners corporation's decision, paid from levies or with a contribution from the owner who asked. The applies to common property. Refusing a request without engaging with it is how a building ends up facing a discrimination complaint. Respond in weeks, not quarters.


State-by-state quick reference

The principle is the same everywhere: common property is the corporation's, the lot is the owner's, and the plan draws the line. The Act, the forum and the builder's warranty periods are not. The warranty periods below are general guides. The exact limit depends on the defect, the contract and the dates, so get advice before you rely on one.

New South Wales

, repair duty in . Fair Trading mediation, then NCAT. Bathroom and balcony membranes are almost always common property. Builder warranties under of the : six years for major defects, two years for others, with a duty of care under the .

Victoria

, repair duty in . A lot owner maintains a service that serves only their lot under . Consumer Affairs Victoria conciliation, then VCAT. Whether a membrane is common property depends on the plan of subdivision. Building claims face a 10-year longstop from the occupancy permit or certificate of final inspection under the .

Queensland

. The format plan does most of the work. In a building format plan the body corporate maintains the outside, but a bathroom membrane is usually the lot owner's. In a standard format plan much more is the owner's. Commissioner's office, then QCAT. The QBCC Home Warranty Scheme covers structural defects for six years and six months, and a claim must generally be lodged within three months of noticing the defect.

Western Australia

. Common property is everything not within a lot, and the strata plan sets the boundary, so a membrane under a balcony defined to the top of the tiles can be common property. State Administrative Tribunal. Building complaints under the generally within six years of completion.

South Australia

/ . Strata disputes go to the Magistrates Court, not SACAT. Statutory warranty proceedings generally within five years of completion under the .

Tasmania

. TASCAT for strata disputes. Membranes are treated much as in NSW, but the plan boundary and any registered by-laws decide. Building claims generally within six years of completion.

Australian Capital Territory

. ACAT. Where the unit plan sets the boundary at the interior face, the membrane is usually on the common property side. The has a 10-year longstop for building actions.

Northern Territory

/ . NTCAT. Maintenance follows the unit plan's boundary definitions. Defect liability runs ten years for structural and two years for non-structural defects, and home warranty insurance is mandatory for work over $12,000. Building work sits under the .

For terminology across all eight jurisdictions, see the strata terminology reference.


Most repair disputes come down to five legal questions.

Is it common property? Read the registered plan first. In NSW, the in the lists who maintains what, but it only binds a scheme that adopted it as a by-law under .

Can the owners corporation hand the job to an owner? Only in writing and only with the right instrument. In NSW, a common property rights by-law can transfer maintenance to an owner who consents. A special resolution under can decide a repair is inappropriate, but only where safety and appearance are not affected. A committee email does neither.

What happens if it does nothing? In NSW, an owner who suffers loss can claim damages under , confirmed in . The window is six years from awareness under . What the scheme knew matters: did not require an owners corporation to upgrade glass whose danger it had no reason to know about, while ordered an unsafe rooftop balustrade replaced because the owners corporation knew or should have known.

Is it a repair or an improvement? A like-for-like pump, pit or repaint is maintenance. A new colour scheme, a new drain across the courtyard or a ramp changes common property and usually needs a special resolution: in NSW, in Victoria. Capital items belong in the 10-year plan under .

Can the building recover from the owner who caused it? Yes, through the by-law process, not a fine someone made up. In NSW that is a notice to comply under , in Victoria a notice to rectify under , and in Queensland a notice under or . The owners corporation still pays the contractor first.

Insurance sits beside all five. In NSW, requires the owners corporation to insure the building. The policy covers sudden and accidental damage. Wear and tear, gradual seepage and lack of maintenance are the usual grounds for a declined claim, which is one more reason to keep the service log.


Tools for owners and committees

Repairs are where a building's memory matters most. The same leak, the same blocked stack and the same gate motor come back every few years, usually after the committee that dealt with them last time has moved on.

We built UnitBuddy so that history stays with the building:

  • Maintenance log. Every incident and repair, with dates, photos and the contractor's report, so the next contractor sees earlier visits instead of starting from zero.
  • Contractor directory. Jobs, reviews and correspondence kept against the trade they concern.
  • Building condition view. Structure, fire safety, plumbing, electrical, exterior and common areas in one place.
  • Document review. Contractor invoices, insurance certificates and reports moving through one review pipeline.

Free resources you can use today:

Explore the tools · See pricing by building size · Get started


Frequently asked questions

Water is coming through my ceiling. Who pays?

Whoever owns the part that failed. A common property membrane or a shared pipe is the owners corporation's. A burst hose, a tap or a pipe serving only the lot above is that owner's. Get a plumber to name the source in writing, and send written notice to both the owners corporation and the upstairs occupier on day one.

Is my shower membrane mine or the building's?

It depends on the state and the plan. In NSW it is almost always common property. In a Queensland building format plan it is usually the lot owner's. In Victoria and WA, read the registered plan. Silicone and grout are the lot owner's everywhere.

The strata says they can't afford the repair. Can they wait?

Not in NSW. The repair duty under is strict, and a lack of funds is not a defence. The owners corporation can raise a special levy or borrow. Every other state also puts a repair duty on the corporation.

How long do I have to claim against the builder?

In NSW, generally six years from completion for a major defect and two years for other defects under of the . Other states differ, and the clock usually runs from completion, not discovery. Get a lawyer to confirm the dates for your building early.

Will strata insurance pay for it?

If the damage was sudden and accidental, possibly. Gradual leaks, wear and tear and poor maintenance are usually excluded, and the excess can be larger than the repair. An insurer declining the claim does not end the owners corporation's duty to fix common property.

Who fixes a blocked drain?

If the pipe serves more than one lot, the owners corporation. If it serves only your lot and sits inside your lot, you. If the same line blocks every year, ask the committee for a CCTV inspection and a relining quote.

Can the building charge me for damage I caused?

Yes, if a by-law supports it and the evidence links the damage to your lot. The path is a written notice under the state Act and, if needed, the tribunal. An owners corporation cannot invent its own fines.


Keep reading

More guides on UnitBuddy:

Or browse the full blog for everything we have published.


Last updated: 19 November 2026. UnitBuddy publishes general information for Australian strata owners, tenants and committees. It is not legal, building or engineering advice. For advice specific to your scheme, consult a strata lawyer, building consultant or engineer.

What changed in strata this month? Read the strata news for your state, with every figure sourced.

More guides like this