Cracks in Apartment Walls and Ceilings: Hairline or Structural, and Who Pays

Most cracks in an apartment are plaster and paint. Some are the building telling you something. How to tell them apart, why apartments crack, who owns the cracked part, who pays for the engineer and the repair, what to do when the site next door starts digging, and how to log a crack so the answer is on paper. State by state.

By Buddy · · 12 min read

On this pageThe owner briefing
  1. The owner briefing
  2. Quick answers
  3. Is a crack in my apartment wall structural?
  4. Who is responsible for cracks in my apartment ceiling?
  5. When should I worry about cracks in my apartment?
  6. Who pays for an engineer to inspect a crack?
  7. Hairline or structural: how cracks are graded
  8. Why apartments crack
  9. Is the cracked part yours or the building's?
  10. Who pays to investigate and repair
  11. Cracks in a newer building
  12. Construction next door
  13. How to monitor a crack
  14. The state-by-state picture
  15. Owner checklist
  16. Committee checklist
  17. How UnitBuddy fits
  18. Related reading
  19. Sources and further reading

The owner briefing

  • Most cracks in apartments are cosmetic: plaster, paint and cornice joints moving as the building dries and the seasons change. A crack that grows, runs diagonally, or comes with sticking doors, rust stains or water needs a structural engineer.
  • Who pays follows the part that cracked. The structure is usually the owners corporation's to investigate and repair, though the plan decides exactly where the line sits. Internal partition walls and paint are usually yours.
  • Measure before anyone fills it. A dated photo with a ruler, repeated every month, is worth more than any number of emails saying "it's getting worse".

A crack over a door frame doesn't drip or smell. It just sits there, and you start wondering whether it was that long last month.

One rule runs through this guide: a crack is evidence. Record it before anyone paints over it.

Quick answers

Is a crack in my apartment wall structural?

You can't tell from the width alone, and neither can the strata manager. As a rough guide, hairline cracks under about 1 mm that stay the same size are usually shrinkage or movement in plaster and paint. Cracks of 5 mm or more, cracks that keep growing, diagonal cracks from the corners of doors and windows, cracks where one side has moved out of line with the other, and cracks with rust stains or water need a structural engineer. The engineer decides, not the width.

Who is responsible for cracks in my apartment ceiling?

It depends on what cracked. The concrete slab above you is part of the building's structure, so in most buildings the owners corporation investigates and fixes it. In NSW, a scheme that adopts the government's common property memorandum also puts original plastered ceilings with the owners corporation, but leaves the painting to you. A false ceiling an owner added later belongs to that owner. Check your plan and by-laws, then the state-by-state picture.

When should I worry about cracks in my apartment?

Straight away if a crack opens suddenly, you hear a bang, doors or windows jam overnight, or concrete falls. Get people out, call 000 if anyone is at risk, then tell the owners corporation in writing. Otherwise, worry when a crack grows between measurements, when it's wider than a few millimetres, when it runs through a column, beam, slab or balcony, or when it lets water in.

Who pays for an engineer to inspect a crack?

If the crack is in common property, or might come from it, the owners corporation pays as part of its duty to repair. If the engineer finds the cause is an owner's renovation or something inside a lot, the repair cost can move to that owner. If you hire your own engineer, you pay, at least at first.

Hairline or structural: how cracks are graded

There's no single Australian rulebook for cracks in apartment buildings. The best-known scale comes from AS 2870, the Australian Standard for residential slabs and footings, which grades damage to walls mainly by crack width. NSW Fair Trading reproduced it in its Guide to Standards and Tolerances 2017, which Building Commission NSW now publishes. In summary:

CategoryWhat it usually looks likeApproximate crack width
0, negligibleHairline cracksUnder 0.1 mm
1, very slightFine cracks that don't need repairUnder 1 mm
2, slightEasy to see and easy to fill; doors and windows may stick a littleUnder 5 mm
3, moderateA small piece of wall may need replacing; doors stick, pipes can break, rain can get in5 to 15 mm, or a group of cracks of 3 mm or more
4, severeSections of wall replaced; frames distort, walls lean or bulge15 to 25 mm, depending on how many cracks

Three cautions. The scale was written for houses, so it won't tell you whether a 2 mm crack in an apartment's transfer beam is fine, though it's still the clearest published yardstick. The guide lets the limits rise by 50 per cent for easily repaired plasterboard. And width isn't everything: location, the job the structure does and the crack's history all count. A stable 2 mm crack can matter less than a 0.5 mm crack that was 0.2 mm in March.

For new work, the guide is stricter about linings. Cracks in plasterboard walls, ceilings, bulkheads and cornice joints are defective if they're there at handover, or exceed 1 mm within 24 months of completion and can be seen from a normal viewing position (items 10.14 and 10.15). Slight cracks in walls and slabs are to be monitored for 12 months before anyone decides (items 2.10 and 3.2).

Why apartments crack

Six usual suspects. The engineer says which one.

Shrinkage. Concrete, render and plaster shrink as they dry. Fine cracks at plasterboard joints, along cornices and where walls meet ceilings are the classic signs, most often in the first couple of years.

Slab movement. Concrete floors sag slightly under load and can keep creeping for years. A partition built tight under a slab can crack as the slab settles onto it.

Movement joints missing or covered. Buildings need control joints so materials can move. The NSW guide treats cracks in render as defective where recommended movement joints weren't installed, and treats render laid across a movement joint as defective (items 10.6 and 10.7). A crack running dead straight along a rendered-over line is often this.

Different materials meeting. Plasterboard against a concrete column moves differently on each side. The guide has a separate item for cracks at junctions of dissimilar materials (item 10.16).

Water. Water that reaches the steel inside concrete can rust it. Rust takes up more room than steel, so it cracks the concrete around it. White powder or crusts on a slab are another water symptom, covered in our efflorescence explainer.

Work nearby. Excavation, piling and demolition next door can move a building. So can an upstairs renovation that removed a wall someone assumed wasn't load-bearing.

Opal Tower is the extreme case: a bang on Christmas Eve 2018, cracking on level 10, and police saying the building had moved 1 to 2 millimetres. Most buildings will never see that. It's still why a sudden new crack gets a same-day phone call.

  1. Photograph and measure the crack
  2. Report it in writing
  3. Engineer finds the cause
  4. Structure, lining or owner's work?
  5. Structure: owners corporation repairs
  6. Partition, paint or owner's work: the owner
How the cause of a crack decides who repairs it.

Is the cracked part yours or the building's?

Responsibility follows the part that cracked, not the room it's in. Our lot versus common property guide explains the boundary.

The structure. Columns, beams, load-bearing walls, slabs and external walls are usually common property. Where a plan puts part of them inside a lot, Queensland and the ACT still make the body corporate or owners corporation keep them sound (see the table below). In NSW, the owners corporation must keep common property in good and serviceable repair under of the , and lack of money is no excuse.

The linings. This is where the arguments start. In NSW, a scheme can adopt the common property memorandum in the as a by-law under . Where it's adopted, it puts:

  • common property walls, and plastered and vermiculite ceilings, with the owners corporation, but the painting with the lot owner
  • false ceilings installed when the plan was registered with the owners corporation, and ones an owner added later with that owner
  • internal walls that aren't common property, and paintwork inside the lot, with the lot owner

So in NSW, cracked plaster on a boundary wall or the original ceiling is usually the owners corporation's to fix, and you repaint. A cracked partition between two of your rooms is usually yours, unless the slab above moved it. Fix the cause first and argue about the plaster afterwards.

Who pays to investigate and repair

The investigation. The duty to repair common property includes finding out what's wrong with it. An owners corporation that won't send an engineer to a cracked column because "it's probably cosmetic" is guessing with everyone's building. If the crack is inside your lot but might come from the structure, ask the owners corporation to investigate and be ready to give access.

The repair. If the cause is common property, the owners corporation repairs the structure and, usually, the plaster damage that comes with it. In NSW, an owner who suffers loss because the owners corporation failed in its duty can claim damages. Forcing a strata scheme to fix a defect covers the steps and time limits.

Owner-caused damage. If an owner removed a wall, overloaded a floor or let a leak run, the cost can move to them. In Queensland, of the lets the body corporate recover the costs as a debt from a person whose actions caused or contributed to the damage. In the ACT, of the lets the owners corporation recover from a member whose wilful or negligent act made the work necessary. Structural work inside a lot needs approval first; our renovation approvals guide explains which kind.

Insurance. Strata building insurance is mostly about sudden events, and a crack that grew slowly usually isn't one. CHU, a strata insurer, says defects are "often excluded from property cover" (CHU, September 2024). A declined claim is not a reason not to repair.

The order. Cause, then structure, then plaster, then paint. I'd pay for an engineer before a painter every time. A filled crack can't tell anyone whether it was moving.

Cracks in a newer building

In a building only a few years old, the crack may be a defect the builder has to pay for. The owners corporation still has to make it safe now, with the defect claim running alongside, and warranty clocks usually start at completion. Two posts cover the law:

In NSW, new strata buildings not covered by the Home Building Compensation Fund go through the strata building bond and inspections scheme. The NSW Government says the developer lodges a bond of 2 per cent of the contract price, an independent inspector reports 15 to 18 months after completion and again at 21 to 24 months, and the bond pays for defects in the final report. Give the inspector your crack log.

In the Building Commission NSW 2025 survey, occupants were the first to spot serious defects in 63 per cent of affected buildings, and bond inspections in 12 per cent (detection lag analysis). Your dated photos may be the building's best evidence. Use an engineer who works for the owners corporation, not the builder.

Construction next door

Once the excavator arrives, every unrecorded crack becomes "pre-existing".

  • Ask for a dilapidation report: a dated survey of your building's condition and existing cracks, before work starts and again when it finishes. Ask the developer next door to commission one, and ask for the pages covering your lot.
  • Read the development consent on the council's DA tracker. In NSW, consents carry a prescribed condition about shoring and the adequacy of adjoining property ( of the ). Look for conditions about protecting neighbouring buildings.
  • In Victoria, watch for a protection work notice under . The Victorian Building Authority says an adjoining owner has 14 days to respond, and that the survey should record existing cracks and defects. Make sure the notice reaches the committee and someone answers it in time.
  • Fit crack monitors before work starts and read them weekly while digging or piling is under way.

If cracks appear or grow, the owners corporation claims for common property and you claim for your lot. Write to the developer and its builder straight away, with photos.

How to monitor a crack

You need a ruler, a pencil and a calendar.

  1. Photograph it square-on with a ruler or crack-width card in the shot, from the same spot each time, with the date in the frame.
  2. Mark the ends with a pencil line and the date, so you can see if it runs further.
  3. Measure the width at two or three marked points.
  4. Fit a tell-tale crack monitor on cracks that matter: two overlapping plates fixed either side, with a grid that shows movement in millimetres. Ask the owners corporation before fixing anything to common property.
  5. Read it monthly for a year, the monitoring period the NSW guide uses. Note the season, because some cracks open in summer and close in winter.
  6. Keep one log and send the owners corporation an update whenever something changes.

The state-by-state picture

Everywhere, the owners corporation looks after common property and the plan sets the boundary. The details, the forum and the building regulator vary. Warranty periods for builder defects are in the state-by-state defects guide.

StateWho repairs the structureStrata disputesNew-building defects
NSWOwners corporation repairs common property (); linings follow the memorandum if adopted ()NSW Fair Trading mediation, then NCATBuilding Commission NSW
VicOwners corporation repairs common property (); the owner keeps lot parts that affect other lots or common property in repair (); the plan of subdivision sets the boundaryInternal dispute process, then VCATVictorian Building Authority; Domestic Building Dispute Resolution Victoria
QldBody corporate keeps structural common property sound and, in a building format plan, foundations, roof structures and load-bearing framework even inside a lot ()Commissioner's office, then QCAT where neededQBCC
WAStrata company repairs common property whether damage comes from wear and tear, inherent defect or any other cause ()State Administrative TribunalBuilding and Energy
SAStrata corporation administers and maintains common property (); by default a unit's boundary is the inner surface of its walls ()Magistrates Court (), not SACATConsumer and Business Services
TasBody corporate keeps common property in good and serviceable repair (); by default the boundary is the centre of the wall, floor or ceiling ()Recorder of Titles (), appeals to TASCATCBOS
ACTIn buildings with class A units, the owners corporation maintains load-bearing walls, columns, footings, slabs, beams and balconies, common property or not (), and can sue over structural defects ()ACATAccess Canberra
NTBody corporate manages common property ( of the ); detailed duties sit in the scheme's management moduleNTCAT ()NT Consumer Affairs; Building Practitioners Board

SA schemes under the , older NT schemes under the , and Queensland schemes on other modules follow their own rules.

Owner checklist

Committee checklist

How UnitBuddy fits

We built UnitBuddy to give a building one shared record that stays when committees and strata managers change. Crack photos, engineer's reports and dilapidation surveys sit in the documents library with their dates. Repair decisions are recorded with the committee's reasons, notices tell owners what's happening, and structural repairs go into the ten-year capital works plan. UnitBuddy doesn't hold or move money.

Sources and further reading

General information, not legal, building or engineering advice. For a crack in your building, get a structural engineer's opinion and, if a claim is likely, advice from a strata or building lawyer.