Committees & Records
NSW Initial Maintenance Schedule: What the Developer Must Hand Over and How to Check It
In NSW the developer must prepare the initial maintenance schedule on the standard form and give it to the owners corporation before the first AGM. Here is who prepares it, what it must contain, how it feeds the 10-year capital works fund plan and the building bond inspections, and how to check it line by line.
By Buddy · · 13 min read

On this pageThe owner briefingOn this page
- The owner briefing
- Quick answers
- Who prepares the initial maintenance schedule?
- Does the initial maintenance schedule have to be given at the first AGM?
- What changed for the IMS in the strata reforms of 1 April 2026?
- Initial maintenance schedule vs capital works plan: what's the difference?
- Does the owners corporation have to follow the IMS?
- What the initial maintenance schedule is
- What the standard form asks for
- Multi-storey schemes: the independent surveyor
- How the IMS feeds the 10-year capital works fund plan
- The IMS, the building bond and defect inspections
- Review checklist: what to check line by line
- If the developer doesn't provide one, or provides a poor one
- What other states require at handover
- Committee checklist for the first year
- How UnitBuddy fits
- Related reading
- Sources and further reading
The owner briefing
- The developer (the "original owner") must prepare the initial maintenance schedule on the NSW standard form and give it to the owners corporation at least 14 days before the first AGM.
- For buildings of three or more storeys with stacked lots, an independent quantity surveyor must certify the schedule and the first-year levy estimates.
- The schedule is not your capital works plan. It is the raw material for it, and a developer can later use it against you in a defect dispute.
The initial maintenance schedule, or IMS, is one of the few documents in a new building that the developer has to write for the owners. It lists every piece of common property that needs servicing or inspection, how often, and what it costs. Since 1 April 2026 it has a fixed format in NSW, and for most apartment buildings someone independent has to check it.
Most first committees file it with the other handover PDFs and never open it again. This guide explains what it should contain, what to check, and what to do when it is thin or missing.
Quick answers
Who prepares the initial maintenance schedule?
The original owner, which is usually the developer. Section 115 of the Strata Schemes Management Act 2015 says the original owner "must cause" one to be prepared for the common property. The developer can hire a consultant to write it, but the legal duty stays with the developer. In a multi-storey scheme, an independent surveyor then has to review and certify it (s 115(2A)).
Does the initial maintenance schedule have to be given at the first AGM?
Earlier. NSW Government guidance says the original owner must give it to the owners corporation at least 14 days before the first AGM. It is one of the handover documents listed in s 16, and the first AGM agenda must include an item to consider it (s 15). If it doesn't arrive, the owners corporation can ask NCAT to order the developer to hand it over (s 17).
What changed for the IMS in the strata reforms of 1 April 2026?
Three things. The schedule must now be in the form prescribed by the regulations (s 115(2); Regulation cl 29). In a multi-storey scheme, an independent surveyor must certify the schedule and the first-year levy estimates (s 115(2A)). And the developer must give the owners corporation evidence of that certification at least 14 days before the first AGM (s 16(1A)). The surveyor section has the detail.
Initial maintenance schedule vs capital works plan: what's the difference?
The IMS is the developer's list of routine servicing and inspections, priced at today's cost. The 10-year capital works fund plan is the owners corporation's own forecast of major spending and how it will be funded (s 80). The owners corporation must consider the IMS when it prepares its first plan (s 80(1A)). You never adopt the IMS. You build the plan from it, and the plan replaces it as your working document.
Does the owners corporation have to follow the IMS?
Not as a legal duty. The Act says the owners corporation is not required to comply with it (s 115(3)). But a tribunal or court can consider the schedule when deciding whether a defect or damage could have been avoided (s 115(4)). Skipping the inspections it lists can weaken a later defect claim.
What the initial maintenance schedule is
The note to s 115 says its purpose is to tell the owners corporation about "obligations and costs" for maintaining common property. In practice, it is the building's first servicing manual: what is there, who made it, who installed it, what needs doing and how often.
It covers common property only. Your own lot's fittings are not in it. It is also not a defect report. A developer who lists "inspect balcony membranes annually" is not admitting the membranes are faulty. A developer who leaves membranes off altogether has handed you a gap to fix.
What the standard form asks for
The standard form is titled "Initial maintenance schedule" and is prescribed under clause 29 of the Strata Schemes Management Regulation 2016. NSW Fair Trading publishes it in Word and Excel. The form says its text cannot be changed.
It must contain a maintenance and non-invasive inspection schedule for anything on common property where that work is reasonably needed to prevent damage or failure. For each item, the developer must give:
- whether maintenance, inspection or both are needed
- a description of the work
- how often it is needed
- the estimated cost per maintenance activity or inspection, as at the year the schedule is completed
- the installer's name and contact details
- the manufacturer's name and contact details
The manufacturer's manual or maintenance requirements and the manufacturer's warranty must be attached for each item, if they exist.
The items sit in 17 fixed categories: structural components, exterior materials and finishes, doors and windows, roofing, interior materials and finishes, electrical, plumbing, HVAC, fire safety, lifts and escalators, technology and communication, accessibility infrastructure, landscaping and exterior elements, amenities and facilities, furnishings and fixtures, car parking, and waterproofing systems. Each category lists typical items, and most have an "Other (specify)" row. The item column says "indicate if none", so a blank row is not the same as "we don't have one".
Multi-storey schemes: the independent surveyor
A multi-storey scheme, as the Act defines it, has at least one building with more than two storeys above ground, with all or part of one lot above another (s 4). The ground level counts as a storey. Most apartment blocks qualify. Townhouses side by side usually don't.
For these schemes, before the first AGM the developer must engage:
- an independent surveyor to review the IMS and certify that it was prepared in the prescribed form, and
- an independent surveyor, or a person of a class the regulations prescribe, to review the estimates of contributions to the administrative fund and capital works fund and certify that they meet the expected spending for the year ahead, based on the expenses the developer provided (s 115(2A)).
An independent surveyor is a Certified Quantity Surveyor with the Australian Institute of Quantity Surveyors, or a Chartered Quantity Surveyor with the Royal Institution of Chartered Surveyors, who is not connected to the developer (s 4). NSW Government guidance lists the connections that disqualify a surveyor, such as being a relative, employee, business partner or financial backer of the developer.
Read the certification carefully. The surveyor certifies that the IMS is in the prescribed form. That is a check on format, not a promise that every item is there or every cost is right. The levy certification is "based on the expenses provided by the original owner". If the developer left the lift contract out of the expenses, the surveyor may not have priced it.
The original owner must hold the first AGM within 2 months after the initial period ends (s 14). NSW Government guidance says a late first AGM or late handover documents can cost the developer up to $11,000 plus $220 for each day it continues. A breach of the IMS and surveyor rules can cost up to $11,000 for an individual or $55,000 for a corporation.
How the IMS feeds the 10-year capital works fund plan
Every NSW owners corporation must have a 10-year capital works fund plan, starting from the first AGM (s 80(1)). It must consider the IMS when it prepares the first one (s 80(1A)). The plan must be in the prescribed form (s 80(4)) and finalised by the end of the AGM after the one it was prepared for (s 80(5)). For a new building, that means the first plan should be settled by the end of the second AGM. The first AGM agenda includes an item to discuss it (s 15).
The two documents answer different questions:
| Initial maintenance schedule | 10-year capital works fund plan | |
|---|---|---|
| Who prepares it | The developer | The owners corporation |
| What it covers | Routine servicing and inspections of common property | Major repairs and replacements over 10 years |
| Costs | Per activity, at the year it was completed | By year, inflated, with a funding source |
| Legal force | The owners corporation doesn't have to comply (s 115(3)) | Carry it out "so far as practicable" (s 80(7)) |
| Review | Not reviewed. It is a one-off handover document | At least every 5 years (s 80(3)) |
Routine servicing from the IMS, such as quarterly fire checks or monthly lift servicing, usually belongs in the administrative fund budget. Replacement and major work belongs in the capital works plan. Our capital works fund plan guide explains how to prepare the plan on the standard form.
The IMS, the building bond and defect inspections
Many new NSW apartment buildings also go through the strata building bond and inspections scheme. It covers residential building work that isn't covered by home building insurance (s 191), which in practice means most high-rise apartment buildings. The developer lodges a bond of 2% of the contract price before applying for an occupation certificate (s 207). A building inspector reports between 15 and 18 months after completion (s 199), and again between 21 months and 2 years (s 201). The bond can pay for fixing defects identified in the final report (s 209).
The IMS and the bond process meet in three places:
- The interim inspection. Give the building inspector the IMS, the manuals and the owners corporation's servicing records. If a system listed in the IMS is failing, the inspector should know it was serviced on schedule.
- The final report. The final report generally can't raise new defects that weren't in the interim report (s 201(3)). Raise every concern before the interim inspection.
- Defect claims. Section 115(4) lets a tribunal or court look at the IMS to decide whether damage could have been avoided. A builder facing a waterproofing claim can point to the line that said "inspect sealants every 12 months" and ask for your records. The statutory warranties under section 18E of the Home Building Act 1989 still apply, but your maintenance history becomes part of the argument.
My view: treat the IMS as evidence the developer will later use against you if you ignore it, not as a brochure. Do the non-invasive inspections it lists, keep the reports, and record any item you deliberately chose not to follow and why.
The developer can't vote, or use a proxy vote, on building defect matters at general meetings (Schedule 1, cl 15). That includes approving the building inspector (s 195).
Review checklist: what to check line by line
Go through the schedule with the plans, the fire safety schedule and a walk around the building. These are the gaps I would look for first.
Whole document
- It is on the current standard form, not a consultant's own template with similar headings.
- The scheme address, plan number and completion date are filled in.
- For a multi-storey scheme, the surveyor certification and the independence evidence came with it, at least 14 days before the first AGM.
- Every row is either filled in or marked "none". Blank rows are unanswered questions.
Each item
- The frequency matches the manufacturer's manual, not a round number. Warranties often depend on the servicing interval.
- The cost is per activity, not a lump sum for the year. "$0" or "included" needs an explanation.
- Installer and manufacturer contact details are real businesses you can call.
- Manuals and warranties are actually attached, not "available on request".
Items commonly missed or underpriced
- Waterproofing: balcony and podium membranes, sealants for joints and penetrations, planter boxes over the car park.
- Plumbing: flexi hoses, tempering valves, backflow prevention testing, grease traps, on-site stormwater detention, sewage and stormwater pumps and pits.
- Fire: fire dampers, stair pressurisation, basement ventilation, fire seals and fire doors. Cross-check against the fire safety schedule.
- Roof: anchor points and height safety systems, which usually need periodic certification.
- Car park: roller doors and gate motors, car stackers, boom gates, EV chargers.
- Energy and data: embedded networks, solar panels and batteries, access control, intercoms, the building management system.
- Façade access: building maintenance units, window cleaning cradles and gantries.
- Shared facilities: pool plant and safety features, gym equipment, waste chutes and compactors.
If an item exists in the building and isn't in the schedule, write it down. That list becomes your first request to the developer and your first additions to the capital works plan.
If the developer doesn't provide one, or provides a poor one
- Minute it at the first AGM. Record what was received, when, and what is missing. The agenda already has items for the IMS, the handover documents and building defects (s 15), so you won't need a new motion to raise it.
- Ask in writing. Send the developer a list of missing items, missing attachments and blank rows, with a deadline. Keep it factual.
- Report it. Breaches of the IMS and surveyor rules carry penalties. NSW Fair Trading is the regulator to tell.
- Apply to NCAT. NCAT can order the original owner to provide a document that should have been delivered (s 17).
- Fill the gap yourself. Don't wait for the developer to plan your maintenance. Get service contractors to inspect and quote, and fold their results into the first capital works plan. A building consultant or quantity surveyor costs money now, but less than a missed membrane inspection later.
What other states require at handover
Only NSW has a developer-prepared maintenance schedule on a mandatory standard form with independent certification. Other states put more weight on the scheme's own maintenance or sinking fund plan, and they don't even agree on what to call it. Our guide to sinking fund vs capital works fund terms sorts out the names. Where I couldn't confirm a rule in the legislation, the table says so.
| State | Developer's handover obligation | The scheme's own forward plan |
|---|---|---|
| NSW | IMS on the standard form, at least 14 days before the first AGM; surveyor certification for multi-storey schemes (s 115, s 16) | 10-year capital works fund plan, reviewed every 5 years (s 80) |
| Vic | I couldn't confirm a developer duty to prepare a maintenance schedule. Check the Owners Corporations Act 2006 | Tier 1 and 2 owners corporations must have a 10-year maintenance plan and a maintenance fund; others may (s 36; Consumer Affairs Victoria) |
| Qld | Under the Standard Module, the original owner gives the body corporate a register of assets, first-year budgets and an estimate of sinking fund spending for the first 10 financial years at the first AGM (s 96) | The sinking fund budget must cover anticipated major spending for at least the next 9 years (s 160). Other modules have their own rules |
| WA | The scheme developer convenes the first meeting within 3 months of registration and hands over the key documents, including warranties and servicing manuals (s 77, s 78) | Strata companies with 10 or more lots need a 10-year plan, revised at least every 5 years (s 100) |
| SA | I couldn't confirm a developer maintenance schedule rule. Check the Strata Titles Act 1988 or the Community Titles Act 1996 | Not confirmed. Check the Act that applies to your scheme |
| Tas | The original owner calls the first meeting within 3 months of registration or once half the lots are sold, whichever is first (Land Titles Office). I couldn't confirm a maintenance schedule rule | Not confirmed. Check the Strata Titles Act 1998 |
| ACT | At the first AGM, the developer gives the owners corporation its maintenance schedule for the common property, with plans, contracts and warranties (Schedule 3, s 3.4 of the Unit Titles (Management) Act 2011) | A 10-year sinking fund plan, approved within 12 months of the first AGM, first reviewed within 4 years and then every 5 years (ss 82, 84 and 85) |
| NT | I couldn't confirm a developer maintenance schedule rule. Check the Unit Title Schemes Act 2009 and its management modules | Not confirmed |
Committee checklist for the first year
How UnitBuddy fits
UnitBuddy gives the building one shared record. You can keep the IMS, the surveyor certification, manuals and warranties in documents, record the plant and equipment as assets, and log the first AGM decisions and follow-up notices to the developer. When you prepare the first 10-year capital works plan, UnitBuddy's planner lets you add each item from the IMS, model the levy, and export the plan on the NSW standard form for the AGM. The record stays with the building when the committee or the strata manager changes.
Related reading
- The NSW Strata Building Bond: How Much, When the Inspections Happen and How to Claim It
- NSW 10-year capital works fund plan: how to prepare it in the standard form
- New developer handover rules: what 2026 buyers should check at the first AGM
- Why a clean first year proves very little about a new apartment building
- NSW strata AGM notice: what it must include and the 14-day rule
Sources and further reading
- Strata Schemes Management Act 2015 (NSW)
- Strata Schemes Management Regulation 2016 (NSW)
- NSW Fair Trading: Initial maintenance schedule standard form (Word and Excel)
- NSW Government: guide to strata law changes for committees and owners
- Consumer Affairs Victoria: owners corporation maintenance plan
- Body Corporate and Community Management (Standard Module) Regulation 2020 (Qld)
- Strata Titles Act 1985 (WA)
- Unit Titles (Management) Act 2011 (ACT)
- Land Tasmania: body corporate and strata schemes
What changed in strata this month? Read the strata news for your state, with every figure sourced.
More guides like this

Guides
Strata Committee Governance in Australia: A Plain-English Guide for 2026
How strata committees actually work in Australia: powers, limits, meetings, voting, removing members, and what the 2026 reforms have changed. State-by-state, written for committee members and owners, not strata managers.
5 May 2026 · 13 min read

Committees & Records
Mixed-Use Buildings: Building Management Committees, Strata Management Statements and Who Pays for Shared Facilities
When apartments sit above shops, offices or a commercial car park, one building can hold several owners corporations. A building management committee and a strata management statement decide who runs the shared lifts, plant and insurance, and who pays for them. This is how it works in NSW, how Victoria and Queensland do it, and what to check before you buy.
19 November 2026 · 13 min read

Committees & Records
The Strata Roll: What It Holds, Who Can See It and How Owners' Privacy Is Protected
Every strata scheme keeps a list of its owners: the strata roll in NSW, the owners corporation register in Victoria, the body corporate roll in Queensland. This guide covers what each state's roll holds, when you must tell the scheme about changes, who can see other owners' details, using them to call a meeting, where the Privacy Act fits, and a checklist for the secretary.
19 November 2026 · 13 min read