Repairs & Maintenance

Lift Out of Order Again? Strata Lift Breakdowns, Maintenance Contracts and Who Pays

The lift is common property, so the owners corporation fixes it and the levies pay. Here is what a lift maintenance contract should cover, how long an outage can reasonably last, what to do when it drags on, and how to plan for replacement, state by state.

By Buddy · · 13 min read

On this pageThe owner briefing
  1. The owner briefing
  2. Quick answers
  3. Who pays when a strata lift breaks down?
  4. How long can a lift be out of order in an apartment building?
  5. What are my rights if the lift is not working?
  6. Who pays for lift replacement in strata?
  7. What should a strata lift maintenance contract include?
  8. The lift is common property, so the scheme fixes it
  9. What a lift maintenance contract should cover
  10. Registration and safety checks
  11. How long is too long?
  12. When the lift stays broken: what owners can do
  13. Residents who depend on the lift
  14. Modernisation and replacement: a capital works item
  15. When an owner or a removalist damages the lift
  16. State by state: the duty and where to go
  17. Owner checklist
  18. Committee checklist
  19. A lift contract review checklist you can copy
  20. How UnitBuddy fits
  21. Related reading
  22. Sources and further reading

The owner briefing

  • The lift is almost always common property. The owners corporation must keep it working, and every owner pays through levies.
  • The maintenance contract decides how fast it gets fixed and what each breakdown costs. Read the exclusions and the renewal clause, not the monthly price.
  • If the lift stays broken, write to the owners corporation, then use your state's dispute process. In NSW you can also claim compensation for loss caused by the failure to repair.

A broken lift is an annoyance on the second floor. On the twelfth floor, with a pram, a walking frame or a fridge delivery, it is a different problem. The law is fairly simple. The hard part is the contract nobody has read since 2014 and the replacement nobody saved for.

Quick answers

Who pays when a strata lift breaks down?

The owners corporation, from levies. A lift that serves more than one lot is common property under almost every strata plan. In NSW the owners corporation must maintain and repair common property under of the , and every other state has a similar duty, listed in the state-by-state table. The exception is damage someone caused, such as a removalist's trolley through the doors. That cost can be recovered from whoever caused it.

How long can a lift be out of order in an apartment building?

No Act I could find sets a number of days. The test is whether the owners corporation is keeping the lift in good and serviceable repair. A same-day call-out for a fault is reasonable. Weeks of silence with no repair date is not. If parts are on order, the owners corporation should tell residents what failed, when the parts arrive and what it is doing for people who can't use the stairs.

What are my rights if the lift is not working?

Put the problem in writing to the strata manager and committee, with dates. If nothing happens, use your state's dispute process. In NSW that means a complaint to NSW Fair Trading, mediation, then an application to NCAT, which can order the repair under . An owner can also claim damages for reasonably foreseeable loss caused by the breach of the repair duty ().

Who pays for lift replacement in strata?

All owners, through the capital works fund (NSW), the maintenance fund (Victoria) or the sinking fund (most other states). If the fund doesn't hold enough, the gap usually becomes a special levy or a loan. NSW schemes must list major works in a 10-year plan under . A lift that falls due in year 12 still needs saving for now.

What should a strata lift maintenance contract include?

What is covered and excluded, an entrapment response time written as a commitment, call-out charges, the term, the renewal notice date and an exit you can use. The contract review checklist below has the full list.

The lift is common property, so the scheme fixes it

The lift car, the shaft, the motor, the controller, the landing doors and the buttons on every floor serve the whole building. Your registered strata plan decides the boundary, but a shared passenger lift sits on common property in almost every scheme. Our guide to common lot vs common property explains how to check.

That puts the lift inside the owners corporation's duty to maintain. In NSW, requires the owners corporation to keep common property in a state of good and serviceable repair and to renew or replace it when needed. The duty is strict. "We don't have the money" is not a defence. Victoria's version is of the . In Queensland the body corporate must keep common property in good condition, and structural common property structurally sound, under of the Standard Module.

So the levies pay for servicing and breakdowns, including the ground-floor owners' levies. And the duty sits with the owners corporation, not the contractor. If the lift company is slow, the owners corporation's remedy is against the contractor. Yours is against the owners corporation.

In NSW, building managers have also had a specific duty since 27 October 2025 to raise problems they know about or should know about. The NSW Government's guide to the strata law changes uses a lift outage and overdue lift maintenance as its examples. If your building has a manager, the lift log is part of their job.

  1. Lift stops
  2. Contractor attends and finds the fault
  3. Covered by the contract?
  4. Yes: contractor repairs, levies already paid
  5. No: owners corporation approves a quote
  6. Caused by someone: recover the cost
Most of the cost of a breakdown is decided by the contract before the lift ever stops.

What a lift maintenance contract should cover

Most of the money in a lift's life goes through one contract. Mark Mcleod of TK Elevator Australia described three common types in Strata Community Australia's Inside Strata in May 2022:

Contract typeWhat it usually coversThe risk you keep
BasicRoutine maintenance only. Call-outs and parts are charged separatelyEvery breakdown is a new invoice. Low monthly price, unpredictable total
ComprehensiveMaintenance plus labour for call-outs and general repairsLong-life, expensive components are excluded, such as motors and drive units
Full comprehensiveServicing, 24/7 assistance and most partsHigher monthly price. Still excludes interference and vandalism

The labels are not standard, so read the exclusions, not the name. Mcleod warns that exclusions often sit in sub-clauses or annexures, and that words like "obsolete" should be tied to a schedule of equipment. Otherwise a contractor can call any expensive part obsolete and bill it outside the contract.

My view: on a lift more than about 15 years old, pay for the cover that takes the big components. A cheap basic contract on an old lift just moves the risk into the admin fund, and the admin fund usually loses.

Then check these terms:

  • Entrapment response. I couldn't find a law that sets a response time. The contract does. Ask for a time measured from the call, 24 hours a day, written as a commitment with a consequence, not a "target".
  • Breakdown response and after-hours rates. Know what a Sunday night call-out costs before it happens.
  • Term and renewal. Watch for automatic renewal for another long term unless the owners corporation gives notice in a narrow window. Put the notice date in the committee calendar the day you sign.
  • Price reviews. A fixed formula, such as CPI, is better than "the contractor's current rates".
  • Exit. Can you end it for poor performance, such as repeated breakdowns or missed response times?

Two state rules help. In NSW, since 1 July 2025, unfair contract terms are banned in standard form contracts for goods or services supplied to owners corporations, according to the NSW Government. A lift company's printed contract is usually a standard form contract. In Queensland, a decision to spend above the major spending limit needs at least two quotes, whether it is made at a general meeting ( of the Standard Module) or by the committee ().

Tender the contract every few years against a written scope, with the last two years of call-out invoices attached. Our guide to what an apartment building costs to run explains why lift contracts are usually the biggest line in the budget.

Registration and safety checks

SafeWork NSW says lifts are plant items that must be registered with it, that people with management or control of a lift must make sure it is regularly inspected and maintained, and that records of inspection and maintenance must be kept. It also says a faulty lift must be taken out of service until it is repaired.

Whether those workplace duties land on your owners corporation depends on the building. SafeWork NSW's strata guidance says a body corporate responsible only for common areas used only for residential purposes is generally not a person conducting a business or undertaking. That changes if it employs a worker, or if the common areas are mixed residential and commercial. Other states have their own work health and safety regulators and registration rules, which I haven't confirmed here.

Whatever your building's status, ask the contractor for the registration details and the latest inspection record, and keep both. If a buyer, insurer or tribunal asks whether the lift was maintained, those papers are the answer.

How long is too long?

No strata Act I checked puts a number of days on a lift repair. The question is whether the owners corporation is doing what a reasonable owners corporation would do to keep the lift in good and serviceable repair. In practice:

  • A fault fixed on the call-out is the contract working.
  • A part on order is fine if residents are told what failed, when the part is due and what happens in the meantime.
  • An old lift that keeps failing is a sign the problem is the lift, not the fault. Patching it again and again isn't maintenance.

Age matters. Andrew Batynski of ABN Lift Consultants told a LookUpStrata webinar (article dated 2 April 2026) that lifts typically reach the end of their economic life between 20 and 30 years, and that owners should start planning at about 20. In a separate LookUpStrata answer (29 April 2026), he said controllers, drives, buttons, indicators and door operators typically need replacing after 10 to 15 years, and some parts become obsolete. When parts for a lift are no longer made, a breakdown can turn into a long outage.

When the lift stays broken: what owners can do

The steps are the same as for any repair the owners corporation won't do. Our guide on how to force a strata scheme to fix a defect has the full sequence. For a lift:

  1. Write it down. Email the strata manager and the committee. Give the dates the lift was out, what you were told, and who in the building can't use the stairs. Ask for the contractor's fault report and a repair date.
  2. Ask for the paperwork. The maintenance contract, the call-out history and any condition report are owners corporation records. Owners can inspect them, in NSW under and in Victoria under . Our guide to inspecting strata records covers the other states.
  3. Escalate in NSW. Since 27 October 2025, NSW Fair Trading can investigate and enforce the repair duty. It can issue a compliance notice requiring specific work (). Mediation comes before NCAT for most strata disputes.
  4. Apply to the tribunal. In NSW, NCAT can make orders where the owners corporation fails to carry out a duty (), including an order to repair. Other states use VCAT, the Queensland Commissioner's Office, SAT, the SA Magistrates Court, TASCAT, ACAT or NTCAT. See the table.
  5. Claim your loss. In NSW, an owner can recover damages for reasonably foreseeable loss caused by the breach of the repair duty (). The NSW Government says owners now have six years, up from two, to bring that claim (). Keep receipts for taxis, storage, delivery surcharges and lost rent.

Outside NSW, tribunals can order repairs, but the rules on compensation differ. Check your state's Act before you put a dollar figure in a letter.

Residents who depend on the lift

For a resident who can't manage stairs, a lift outage means they can't get in or out of the building. The accessibility guide covers this in detail. The short version for lifts:

  • Have a written outage plan. Who calls residents who depend on the lift, who arranges help with shopping or medication, and when emergency services are called. It costs nothing to write.
  • Plan long outages with residents. For a planned replacement, Batynski said manufacture and shipping often take 20 to 26 weeks, and residents of a mid-rise building may be without a lift for around 10 weeks (LookUpStrata, April 2026). Tell people months ahead so they can make arrangements.
  • Expect accommodation claims. Asked about a wheelchair user on the top floor of a seven-storey building during a long lift upgrade, Matthew Jenkins of Bannermans Lawyers said (30 April 2026) that alternative accommodation is likely a reasonably foreseeable loss under if the owner can't use the stairs. Budget for it rather than argue about it later.

Discrimination law can also apply to how a scheme treats residents with disability, including the federal and state laws. Whether it applies to a particular request is a question for advice. Ignoring the request is the one approach that never helps.

Modernisation and replacement: a capital works item

A lift's big costs are not breakdowns. They are the modernisation, where the controller, drive and doors are replaced, and eventually the full replacement. Both belong in the long-term plan, not in next year's admin budget.

What it costs. I couldn't find a published industry benchmark for strata lift modernisation or replacement that I'd trust. The best I found is one data point: an owner told LookUpStrata (May 2026) that their high-rise paid $200,000 to replace a lift in 2022, money it hadn't saved. Prices depend on the number of floors, the number of lifts and the scope. Get an independent lift consultant's condition report and budget estimate for your building.

When it falls due. Estimates differ. Batynski puts the end of economic life at 20 to 30 years. Dakota Panetta of Solutions in Engineering said lift technicians often estimate 15 to 20 years. Plan to the shorter figure and be pleasantly surprised.

How each state plans for it:

  • NSW. The 10-year capital works fund plan under has a lift category. Our capital works plan guide explains the standard form, which also encourages saving for long-life items such as lifts that fall due after year 10.
  • Victoria. A maintenance plan is compulsory for tier one and tier two owners corporations (), and names lifts among the major capital items it must cover.
  • ACT. The owners corporation must prepare a maintenance plan to meet its maintenance obligations ( of the ).
  • Everywhere else. Put the lift in the sinking fund forecast with a year and a dollar figure from a consultant.

Get the consultant before the contractor. A lift company's free assessment is also a sales pitch.

When an owner or a removalist damages the lift

Damage is different from wear. If a move scrapes the car, jams a door or breaks a landing sill, the owners corporation still repairs it first. The duty to keep the lift running doesn't wait for the argument about who pays. Then it recovers the cost.

Moves are the usual cause. Our guide to lift bookings and move-in bonds covers protection curtains, bookings and how to set a bond you can defend. In NSW, no law caps move-in bonds. The only statutory bond rule, , bans bonds for keeping animals.

Recovery beyond the bond depends on the state. In Queensland, the body corporate can recover the share of a maintenance cost fairly attributable to the person whose actions caused the damage, as a debt ( of the Standard Module). Elsewhere, start with the removalist's public liability insurer and the bond. Check your Act before you send an owner an invoice. Strata insurance often won't cover gradual move damage, so don't count on it.

State by state: the duty and where to go

StateThe scheme's duty to maintainLift planning or spending ruleWhere disputes go
NSW of the : good and serviceable repair; strict duty10-year capital works plan ()Fair Trading, mediation, then NCAT ()
Vic of the : repair and maintain common propertyMaintenance plan for tiers one and two (); lifts named in VCAT
Qld of the BCCM Act and of the Standard Module: good condition, structurally soundTwo quotes above the major spending limit (, )Commissioner's Office, then adjudication or QCAT
WA of the Strata Titles Act 1985: good and serviceable repair, renew and replaceNot confirmed; check the ActSAT
SA of the Strata Titles Act 1988: administer and maintain common propertyNot confirmed; check the ActMagistrates Court
Tas of the Strata Titles Act 1998: good condition and serviceable repairNot confirmed; check the ActTASCAT
ACT of the : maintain common propertyMaintenance plan required ()ACAT
NT of the Unit Title Schemes Act 2009: manage common propertyLevies fund maintenance under the NTCAT

"Not confirmed" means I couldn't confirm a lift-specific planning or spending rule, not that none exists.

Owner checklist

Committee checklist

A lift contract review checklist you can copy

How UnitBuddy fits

Lift arguments are usually record arguments. Nobody can say how often it failed, what the contract covers or when the renewal notice was due. In UnitBuddy, the lift sits in the building's asset register with its contract, inspection records, outage notes and decisions in the shared record, and modernisation goes into the capital works plan with a year and a figure. We don't service lifts or hold money. We keep the record that tells the committee what to do next.

Sources and further reading

What changed in strata this month? Read the strata news for your state, with every figure sourced.

More guides like this