The 10-Year Capital Works Plan

How NSW's 10-year capital works fund plan works under section 80, the mandatory standard form introduced on 1 April 2026, the 5-year review rule, Initial Maintenance Schedules, and red flags to spot.

8 min read · Last checked

Every apartment building wears out on a schedule, whether the committee admits it or not. Paint lasts 10 to 15 years. Carpet lasts 10 to 15 years. Roof membranes and hot water plants last 15 to 25 years. Lifts need major modernisation around year 20 to 25.

You have two ways to pay for those bills: save steadily into the capital works fund over a decade so every owner pays their fair share while they enjoy the building, or pretend everything lasts forever and smash whoever happens to own in year 14 with a $30,000 special levy. NSW law backs the first approach through the 10-year capital works fund plan.

The short version

  • Every NSW owners corporation must maintain a 10-year capital works fund plan () — with one tiny opt-out for detached two-lot schemes by unanimous vote ().
  • It must be reviewed at least every 5 years (), and preparing or reviewing it is a mandatory item on every AGM agenda ().
  • From 1 April 2026, a prescribed standard form is mandatory whenever you prepare, revise or replace a plan (, ).
  • For brand-new multi-storey buildings, developers must also hand over a standard-form Initial Maintenance Schedule and surveyor-certified opening levies at least 14 days before the first AGM (, ).

On plan

$94k

Persistent gap

$18k

Fund balance in the roof year: tracking the plan versus a $20k annual gap.

What the 10-year plan actually requires

of the sets out the lifecycle of a 10-year capital works plan:

  1. Start at the first AGM (): Prepare the first 10-year plan taking the developer's Initial Maintenance Schedule into account (), and finalise it by the end of the following AGM ().
  2. Review at least every 5 years (): Costs drift fast. Waiting 10 years to check a forecast guarantees your numbers are hopelessly stale.
  3. Prepare a fresh plan for each new 10-year period ().
  4. Actually use it when setting levies (): Your AGM capital works budget must take the plan into account, and the owners corporation must carry out the plan "so far as practicable" ().
  5. No mandatory licence to write it — but don't cut corners (): The Act says the owners corporation may engage expert assistance. A 6-lot brick walk-up with no lift or basement pumps can reasonably prepare its own plan using Fair Trading's standard template and real trade quotes. A 40-lot building with lifts, fire panels, basement pumps and podium waterproofing should pay a qualified quantity surveyor (typically $3,000–$8,000 for smaller blocks, $8,000–$25,000 for larger complexes) to physically walk the roof and plant room. A $4,000 report that prevents a $200,000 funding shock is a bargain.

Note that the plan is adopted by general meeting resolution — it is not lodged with Fair Trading — but any owner or buyer's inspector can view it (), your funding approach is disclosed on certificates, and NCAT can order a reluctant building to prepare one under .

What changed on 1 April 2026: the mandatory standard form

Before April 2026, one building's capital works plan might be a 90-page engineering forecast while the block next door ran on a half-page spreadsheet. Under and , every new, revised or replacement 10-year plan prepared from 1 April 2026 must use the official standard form titled "10-year capital works fund plan for strata schemes in NSW".

Existing plans prepared before 1 April 2026 remain usable until they come up for review or replacement — you don't need to bin a solid 2024 plan early, though you cannot simply change the cover date on an old spreadsheet and call it revised.

The standard form forces six pieces of truth into the open:

  1. Scheme details and opening Capital Works Fund balance
  2. Current Capital Works levy per unit entitlement
  3. An explicit annual building-cost inflation assumption (no more quietly hiding an unrealistic 2% figure)
  4. Anticipated expenditure for Years 1 to 10 across fixed asset categories, shown in today's dollars and projected forward
  5. Annual totals plus a contingency allowance
  6. A 10-year source-of-funding cash-flow table showing whether planned levies actually cover the bills or dip into deficit

New builds: the Initial Maintenance Schedule (IMS)

If you buy into a brand-new NSW building, your capital works journey starts even earlier. Under , and , the developer must deliver a standard-form Initial Maintenance Schedule (covering 17 fixed building categories, with warranties and manuals attached) at least 14 days before the first AGM.

From 1 April 2026, for multi-storey schemes (more than 2 storeys above ground with vertically stacked lots), the developer must also hire an independent qualified quantity surveyor (AIQS Certified Quantity Surveyor or RICS Chartered Quantity Surveyor) to certify both the standard-form IMS and the first-year admin and capital works levy estimates (). Penalties for skipping handover or certification run up to $11,000 plus $220 per day (and up to $55,000 for corporations on IMS/surveyor breaches).

One clever detail in : the owners corporation isn't legally forced to follow every line of the IMS, but if a defect claim later ends up at NCAT or court, the tribunal can look at whether the building followed the IMS to decide if damage could have been avoided. Ignoring the handover schedule weakens your warranty position.

How to read a 10-year plan and spot red flags

When a 10-year plan lands in your AGM pack (or a pre-purchase strata report), ignore the glossy cover and look straight at four numbers:

  1. Total 10-year forecast spend
  2. Current Capital Works Fund balance
  3. Recommended annual contribution (what the plan says you need to collect)
  4. Actual annual contribution (what the AGM has been collecting)

Six red flags that signal a special levy ahead

Red flagWhy it hurts owners
A persistent gap between recommended and actual leviesIf the plan recommends $60,000/year and the building votes $25,000/year to keep quarterly fees looking pretty, you are building a $350,000 hole over a decade.
Lowball 2% inflation assumptionsAt 2% inflation, a $100,000 roof job grows to ~$122,000 in 10 years. At 5% — closer to recent Australian construction inflation — it hits $163,000.
Missing major assetsCheck that lifts, roof membranes, facade painting, fire panels, basement pumps, driveways and balcony waterproofing are actually listed.
Desktop refreshes without a site visitUpdating a 2018 spreadsheet from an office desk is how lift replacements stay magically stuck in "Year 8" for ten years straight.
Suspiciously round placeholder numbers"$50,000 for building works" with no breakdown usually means nobody inspected the asset.
Balance below 20% of the next 5 years' spend in a 15+ year old buildingAs a rule of thumb (not a statutory figure), older blocks generally want a buffer covering roughly 30–50% of the next five years' forecast works; under 20% usually means a special levy is around the corner.

Check your understanding

1. Your owners corporation had a solid 10-year capital works plan prepared in 2024. On 1 April 2026, NSW's new mandatory standard form commenced. Do you have to throw out your 2024 plan immediately?

2. How often must a NSW owners corporation formally review its 10-year capital works fund plan at a minimum?

3. You are reviewing a draft 10-year plan that uses 2% annual inflation and omits the building's 22-year-old lift. What is the real-world risk if owners adopt it as written?

Go deeper