Meetings, votes and by-laws
Scheme by-laws and s 96 contravention notices
How NT Schedule 2 default by-laws, Schemes Supervisor certification and s 96 Contravention Notices (strict liability offence up to 20 penalty units) work.
3 min read · Last checked
On this pageKey Schedule 2 default by-laws (2009 Act)On this page
In a post-2009 Northern Territory unit title scheme, everyday rules sit in your scheme statement and the default by-laws in Schedule 2 of the Unit Title Schemes Act 2009 (s 95). Legacy 1975 plans use the default articles in Schedule 1 of the Unit Titles Act 1975 and any registered by-laws.
Key Schedule 2 default by-laws (2009 Act)
Unless modified by your scheme statement, Schedule 2 sets four baseline rules every owner should know:
- Default by-law 1: Prohibits improper conduct — including loud noise — that unreasonably affects other people's enjoyment of the scheme.
- Default by-law 2: Requires written approval before physically disturbing common property (such as drilling into a boundary wall).
- Default by-law 4: Requires written approval before changing a unit's external appearance or displaying items visible from outside.
- Default by-law 7: Approvals under the default by-laws are granted by majority resolution (s 79(6)), may include conditions and time limits, and stand until cancelled by majority resolution.
Changing by-laws: Schemes Supervisor certification
Under section 95A, changing a scheme's by-laws requires a special resolution, followed by certification by the Unit Title Schemes Supervisor and lodgement with the Registrar-General. Changing an exclusive use by-law generally requires a unanimous resolution (s 97(3)).
Enforcing breaches: the s 96 Contravention Notice
The Northern Territory gives 2009-Act bodies corporate one of the sharpest breach-notice tools in Australia under section 96 of the Unit Title Schemes Act 2009:
- The body corporate (or committee/manager acting on its behalf) serves a written contravention notice on an owner or occupier specifying the breach and a reasonable time to stop or fix it (no prescribed statutory form).
- Failing to comply with a valid contravention notice is a strict liability offence carrying a maximum penalty of 20 penalty units (approx. $3,880), subject to a reasonable-excuse defence.
- The body corporate can also remedy the breach itself and pursue compensation from the person responsible, or seek binding orders at NTCAT (no mandatory pre-filing mediation step).
Note that a section 96 contravention notice applies only to 2009-Act schemes — not legacy 1975 plans. And under neither Act can a body corporate evict a tenant; terminating a lease sits under the Residential Tenancies Act 1999 (NT).
Contravention notice for a by-law breach (UTSA 2009 s 96)
Check your understanding
1. Under s 96 of the Unit Title Schemes Act 2009 (NT), what is the maximum penalty for failing to comply with a contravention notice without a reasonable excuse?
General information only, not legal advice.