Tasmania's six-year statutory warranties for residential building work, disputes through Building Standards Tasmania, the 10-year cut-off and the body corporate's rights under the developer's contract.

4 min read · Last checked

A defect claim in Tasmania runs on two clocks: the statutory warranties in the , and the outer limit for damages in the . Miss either and the claim is gone, however good the evidence. The 2016 Act replaced the Housing Indemnity Act 1992.

The statutory warranties

The warranties cover work on "residential buildings", which the Act defines as National Construction Code class 1a houses, class 2 apartment buildings and their associated class 10 structures (), where the contract price is $20,000 or more ().

The builder warrants that:

  • the materials are suitable ()
  • the work complies with all laws ()
  • the work is done in an appropriate and skilful way, with reasonable care and skill ()
  • the work follows the plans and specifications ()
  • the building will be suitable to live in ()
  • the work is carried out with reasonable diligence ()

You don't need to be the person who signed the building contract. Later buyers inherit the warranties (). Proceedings for a breach must start within 6 years after practical completion ().

The 10-year cut-off

Separately, of the Building Act 2016 says a damages action for defective permit or notifiable work can't be brought more than 10 years after the cause of action accrues, usually the date of the occupancy permit. For low-risk work the limit is 6 years.

Who claims for common property

In an apartment block, the defect is often in common property: the roof, the facade, a shared membrane. The body corporate steps into the developer's shoes. of the Strata Titles Act 1998 gives it the developer's contractual rights to damages against the builder for defective work, on its own behalf for common property or for the owners affected.

That only helps if someone acts. In a new building, put a defect inspection on the agenda for the first AGM, which the developer must hold within 3 months after registration or once half the lots are sold, whichever is earlier (). An inspection report in year one is cheap next to a claim lost in year seven.

Making a claim

  1. Record the defect with dated photos and reports
  2. Write to the builder asking for repair
  3. Lodge a notice of dispute within 6 years of practical completion
  4. Mediation under Part 9 of the 2016 Act
  5. TASCAT decides certain matters
The dispute path under the Residential Building Work Contracts and Dispute Resolution Act 2016.

If the builder won't fix it, lodge a notice of dispute with the Director within 6 years of practical completion (). Since 1 October 2026 that service sits with Building Standards Tasmania. The dispute goes to mediation, and TASCAT can decide certain matters if that fails ().

For small items at handover, use the defects document process in . List everything, however minor, before you sign off.

Check your understanding

1. A Hobart apartment block reached practical completion seven years ago. Owners now find the builder's waterproofing breached the statutory warranties. What's the problem?